Arrow City Manhattan is an ambitious project by Arrow Engineering located near pen. The Arrow City Manhattan is a proposed mega township right opposite South Mumbai. Arrow City Manhattan plans to offer a picture perfect exquisite new style living with new concept of dream homes come true. The project has various striking features which includes great accessibility, metro train connectivity, schools, hospitals, golf course and various other public facilties which will be highly city level. Arrow City Manhattan is more about style and living with comforts. This upcoming project is located near NH – 17, Mumbai Goa Highway.
This blog lists some genuine comments and reviews on my part regarding few products from India and international. These product vary from latest gadgets, home products, automobiles, hospitals, and few more. Trying to give my best when it comes to providing information. Finally me too a human being who is never error-free..
Subscribe to:
Post Comments (Atom)
Is it closer to Pune?
ReplyDeleteAbhishek, Arrow City Manhattan is near Pen..right on the Mumbai - Goa Highway
ReplyDeletehow long will it take for this project to complete?
ReplyDeleteIt should finish by next year or so.. but the project definitely seems to be happening..Planning to visit next week, will let you know how it looks..
ReplyDeleteHi, I had visited the site of this project. It seems to be promising in the near future. Its like an investment. I have also booked a flat in ARROW CITY. It is approx. 1hr from CBD Belapur.
ReplyDeleteJust keep me posted if any news on this.
ReplyDeleteHI,
ReplyDeletemy friend just booked a plush apartment in arrow city. wat i wanted to knoe is how safe is the investment. with the raging issues of non payment to the farmers. Is it a safe bet
Hey Mr. Anonymous, why not post your name in the blog and let others know about you. By d way congrats for the flat in Arrow Manhattan...
ReplyDeleteHi Soumen..
ReplyDeleteThe project as yet looks promising, the features and highlights seem to amaze everyone, yet if there's anything i would keep updated..You too let me know if find something..
Hi planning to investment in residential flat in this project, how safe and promising from investment perspective - any views please
ReplyDeleteI too have invested in plots in the Arrow Manhattan city. Almost all the money paid which they collect promptly but since 2007 they are postponing it to "next year" which never comes. Also, the only progress is that they are making a boundary wall and a few brick structures looking temporary shelter for the workment at site. No real progress till date. The land extends from Pen to Pooran 150 acres which will take at least a decade ,more if they continue at present speed. Hopelessly slow!
ReplyDeleteHello Rajendra
ReplyDeleteThanks for this piece of information..Definitely would come handy for others who wish to invest in the property.. Please do keep us updated on this..Thanks for visiting, Do stop by!
i would like to know about the bungalow plots where are they located and can u suggest the link to the site map of Arrow Engineering LTD. Group (only for the bungalow plots), and one last thing are there any office floors or industrial commercial buildings in or around this location of NH -17.
ReplyDeleteHello Navneet Singh..
ReplyDeleteThe area where the Arrow City Manhattan plans to come up is a rural area, which has high development prospects in the coming future. At present I would not say that there is much of commercial development happening nearby. But sure in future it may boom..if interested one should carry on by investing now..
http://arrowgroup.us/layout.html is the link for site map as the whole area is been divided into Beta Sectors ranging from Beta Sector 1 to Beta Sector 7. Each sector has been divided into proper slots, allotting plots for bungalows, commercial plot and apartments, specifically Beta Sector 3A and 3B.
But we should also pay attention to the piece of information shared by Mr. Rajendra here..The project is going on real SLOW!
HI EVERY ONE,,
ReplyDeleteI HAVE BEEN ENQUIRING ABOUT THIS PROJECT SINCE 2008 BUT WAS NEVER CONVICED..BUT THIS WEEK I WENT TO THEIR BELAPUR OFFICE...FIRSTLY THEIR OFFICE VERY HUGE,WELL BUILT BUT LOOKS INITIALLY AT RECEPTION LIKE A PUB BUT THEY OFFERED ME A TOMATO SOUP , GOOD HOSPITALITY...THERE AFTER I MET A CHARLIE CHAPLIN JOKER TYPE SALES GUY MR LAXMAN PATIL TALKING IN TOOTI FOOTI ENGLISH , OK HINDI BUT GOOD MARATHI (WHICH I WAS NOT ABLE TO UNDERSTAND).THEN HE EXPLAINED ALL THE DETAILS AND TOOK ME AND MY FAMILY WITH THIRTY MORE IN A ARROW CITY MANHATTAN BUS..BUS AC WAS GOOD BUT SEATS CRAMPED IN ABOUT 40-50 MINUTES WE REACHED THE SITE AT PEN..BUT ONCE I GOT OUT IT WAS HEAVEN..COOL BREEZE ,PLAIN LANDS ,MOUNTAINS FROM VISIBLE DISTANCE...THEIR SITE OFFICE WAS OK , THEY SHOWED US A SAMPLE FLAT(UN FURNISHED) BUT AT 18 LACS FOR 3BEDROOM SEXY BARGAIN....WORK WAS HAPPENING BUT I COULD SEE VERY FEW LABOUR MAY BE APPX 50/60....FROM 2ND FLOOR WITH BINOCULARS THEY SHOWED ME TRACTORS/JCB WORKING MAKING ROADS...AND AFTER ALL THEIR SALES TALKS THEY TOOK US BACK TO OFFICE..I WAS SHOCKED TO FIND THAT LAXMAN HAD ALSO GIVEN HIS LAND FOR THE PROJECT..NOW I HAVE BOOKED A 3BED APARTMENT BY PAYING 1.5 LACS AND HOPE FOR THE BRIDGE TO START EARLIEST AND THE COMPANY SHOULD ACCELRATE PROGRESS AND ONLY ASK FOR FURTHER PAYMENTS ON PROGRESS..PRAVEEN GUPTA,MGR MATERIALS ,HPCL
Hello Mr. Pravin
ReplyDeleteThanks for sharing that piece of information..Will definitely come useful for others while making a deal at Arrow City Manhattan..Congratulations for your purchase by d way... Please do keep us updated about the project..
Hi all,
ReplyDeleteSangeeta
Are you with Arrow city? I too have invested in plots and paid the whole amount which was happily taken without informing of the delays. It has been only promises of 'next year'. Now they say another one and a half year. I have faith in the project but delays make me a bit jittery. Why so slow? Why are they not posting anything on their website about progress on plots? Every time we have to speak to a different salesman in the office to get a different response. So I start having doubts. A good thing would be to keep the investors in the loop by posting information on the website about progress. We who have invested in plots want to know about our plots and not about buildings. They are doing newer projects about building flats but what about delivery of plots that were promised to us 2 years ago. It has been a delay after delay.
Hey Neeta
ReplyDeleteThanks for stopping by. No I am not with Arrow City. This is an independent blog of mine and I have just posted this article about upcoming properties like I do always. The readers who come across this article comment on the recent updates.
So what is your personal view on Arrow project? does it look promising? Has the management said anything bout complaints etc on ur blog?
ReplyDeleteNo Neeta I haven't received any such comment so far.. But you can check the above comments which also include few information which may come helpful for you..Thanks for visiting..
ReplyDeleteHi All,
ReplyDeleteHave you check this below URL;
http://www.complaints-india.com/complaints/8879/Arrow-City-Manhattan-Pen-Big-fraud-GOVT-sleeping.html
Hi,
ReplyDeleteIs this project near to JNPT Nhava Sheva??
please advice exact location.
hi all,
ReplyDeleteShivani
have read a lot of comments on this project and these comments have really left me confused . cant say if this project is genuine ..
Anyways, wld love to visit the site and get some more info
thanks all of u'all for keeping updated
Hey Dhamma..
ReplyDeleteThe exact location for this project is on NH-17, Mumbai - Goa Highway near Pen.
hi all,
ReplyDeleteI have also booked a flat in ar.city manhattan and also paid 2 installments.The only thing I want to know is the project really starting at all or is stuck under some village land dispute.
Hello Cyber King
ReplyDeleteThanks for stopping by..Please do read the above comments and then judge on your own. Nothing can be said in the present situation other than what has been told above by few who have actually visited and booked in the site.
Hi,
ReplyDeleteI came across this blog while searching for updated info on Arrow city project. I had also booked a plot in this project in 2007. There was some progress then and I have already made the requested installment payment (which is close to half of total cost). Since past few years there has been no demand for any further payment and the work has come to standstill. They have got more focused into flats and going full throttle with ads and accepting bookings. I have also read the complaints of this project on various forums. I have already lost a good amount as they are not ready to return the money already paid and i can only wish that in future this project works out. Various investors who bought the plots few years back are still trying to get out of this project. The company promises to return the money in 6 months and after deducting 20% amount. Many people who have requested for returning their money have not yet got it. Please be CAREFUL. Use your judgement and make sure you verify all the documents and visit the site before parting ways with your hard earned money.
Ali, Mumbai
Hi I want to know when they are going to take the second instalment is it going to happen soon or will take time
ReplyDeletewhenever u are going for book the flat pl. dont give any reference(ur freind) to arrow city they will give u 10-15 (as per 2/3 bhk) thousand discount directly to u.
ReplyDeleteotherwise that discount will go to directly that refer person...prashant
Thanks Prashant for the info...
ReplyDeleteIs anyone sure what will be the future of this project.
ReplyDeleteSunil Phadnis
HELLO EVERYONE, I AM INTERESTED IN THIS PROPERTY..ANY UPDATES ON RECENT DEVELOPMENT?
ReplyDeleteHave read the different views and comments. I am one of the few who had invested in a plot in 2007 and since then waiting for the project to come about. Really don't know whether this is genuine or a fraud but these guys are really slow....so invest if you have the patience and the capacity to wait and watch...
ReplyDeletecheers
I have read all above comments and would like to caution investors that this project would only be a reality if government of maharashtra give them the salt lands. These lands are owned by government of maharashtra. Investors should ask for documents of the lands included in this project.
ReplyDeleteBE CAUTIOUS.
Anonymous
hi ,
ReplyDeleteAs everyone is booking flats and plots. I want to know, What kind of documentation they are offering to you ? When Arrow city management is planning for registration of plots and flats.
As the registration will be happening the investor will be more secure on his part.
hello guys,
ReplyDeletei wanted to know regarding the plots, which are in different sq.yds like 200,250,300,500 and 1000. how many floors are permitted and can be constructed on the above mentioned plots?
thanks
well no doubt the work progress is very slow and for mr.PRAVEEN GUPTA,MGR MATERIALS ,HPCL. according to me u could have got 4 to 5.5% discount on your 3 bhk if u are paying in easy installments. (if u pay 100% down payment, then the discount is 10%, official) , u said u got it for 18lacs and official 3 bhk rate is 17,99,999/- so where is the discount, i think u didnt get one.
arrow city manhattan people needs money for their project to go faster towards completion and thats the reason they would have given u good discount no matter if its installments or down payment . if u would have tried a little bit, a u could have got something for your car as well. dont mind, but still its good.
REASON
ReplyDeletearticle in mid day
Date: 2010-08-19 Place: Mumbai
http://www.mid-day.com/news/2010/aug/190810-realty-rates-navi-mumbai.htm
Hello Navneet
ReplyDeleteThanx for sharing this piece of information with us..This article indeed mentions 20% reduction in prices. But though they admit that the price slashing has nothing to do with the airport rumors, yet who knows what the truth is anyways..
Hi All,
ReplyDeleteAs every body is interested in flats and plots. When company is promising for registrations. How any body can apply for loans.
Without approvals and registrations, how to manage loans.
Since for many customers The are just saying registration in 2 yrs. But till now no signs of registrations.
Hi Everyone,
ReplyDeleteI have booked 3 bhk in Arrow city project in May 2010. I have been looking the advertisement since 2007, but till date I cannot see any progress in the construction work. Since last 3 yrs whenever I enquired , they said construction will start in 2 months, but in 3 yrs just entrance gate, nothing else. The project have not yet received any approval from any bank for home loan.I seriously doubt if they have approval for the project and have they acquired the said land? After you do the booking with them ,you never receive any query replied by them, neither any update on the project progress. I suggest to be very cautious before investing with them. Wait for the bank approval for their project before investing.
HI,EVERYONE
ReplyDeletethose who have invested in plot or flat should stop the instalment unless they are ready to registry of the said land or flat. unless we dont come togther they will not take it seriously, so find some time and arrange a day we all will visit the office together,and ask the query.
agree with last poster. lets meet together and visit the office.
ReplyDeletehello everyone,
ReplyDeleteespecially Mr.Anonymous & Ms Sangeeta Chaubal
this is Pavan, I had also booked a plot in this project last year, they gave me a few photocopied documents said that these are the papers of the land and if u want you can get it checked. what i really want to know is what can we check and from where?
Dear Team,
ReplyDeleteNow the arrow is telling that they will start the construction of work in Dec 2011.
3 months before they told me that they will start work at August 2011.
It seems that they will follow the same trend in future and will never start the construction of flats.
Sure, I will send you email with details. and will all meet...
ReplyDeleteHi Sangeeta thanx for providing us with a platform in form of your blogs. Your blogs are really good and keep up the good work
ReplyDeletejust visited their office in Belapur and mr. patil mentioned that the pocession will be end of 2014. The project looks good on paper as they are charging on carpet area. but my doubts is the project worth investing
ReplyDeleteHi Sheyar Kundan
ReplyDeleteThanks for visiting my blog. Good to known you like it. Appreciate your comments
Hello Anthony
ReplyDeleteThanks for visiting. Many visitors have posted their opinions and personal experiences on this page of my blog. Hopefully they will help you decide.
I HAD ALSO BOOKED A PLOT IN THE SAID PROJECT IN THE MONTH OF FEB 11 . I WAS TOLD THAT THE WORK WOULD BEGIN AFTER RAINY SEASON OF 2011 ......LET US SEE WHAT WILL HAPPEN BY THE PROJECT LEADERS.
ReplyDeleteHi All,
ReplyDeleteIf you are planning to meet, Plz let me know also know. Since I booked the plot from last year Oct 2010.But still no progress in project. But now I read in India real estate board forum that investigation is going on for Arrow city - Mr. Vineet Malhotra. Plz check link -
http://www.indianrealestateboard.com/forums/showthread.php/5702-Mumbai-Arrow-City-Manhattan/page6
My mail id is u1kumar2002@gmail.com. Plz contact me for any joint meetings.
Thanks,
if u have bought the plot or apartment in this township just because it will be near 2nd AIRPORT and SEWRI-NHAVA-SHEWA-SEA LINK then please get the refund from the builder because 2nd AIRPORT and SEWRI-NHAVA-SHEWA-SEA LINK will not happen in this area and this is a inside news which i m sharing with u guys.
ReplyDeletei got my refund from builder
Are you sure that Airport and Nhava Shewa project will not come.Today only I visited site and their office.
DeleteOn the hopes of these two things I was planning to book a plot . The current rate id Rs 550 for beta sector-1& 2 and Rs 666 for beta sector 6
I am confused now
Nitin
Are you sure that airport and Nhava-Shewa project will definitely not come.Because on the future prospects of these two things ,today only I visited the site and their office and was thinking of booking a plot
DeleteThe rate they told me is Rs 551/ per sq.ft and Rs 666/per sq.ft
Now I am confused
Nitin
By now, it should be clear to everyone that something is seriously wrong with this project. Just search the net and you'll find a lot of info about people having issues w/this project. Please don't fall prey to big ads.
ReplyDeleteif this guy got his money back, i guess we all should try to get our money back from the builders, they are not entertain my calls and seriously think that these builders are just like SPEAK ASIA company.
ReplyDeletegod please get my money from these evil people.
Anonymous said...
ReplyDeleteYes, we all meet and ask refund money.
Because they do not know when the work will start
Why we all invest money without any gain.
everyone pls lets know when all we will meet and ask to the builder.
hello friends,
ReplyDeleteI went deep into arrow group for some research and found out that it is a total fake project and they are planning to move out of the country in 4-5 months,so please friends TAKE ALL YOUR MONEY BACK B$ ITS TOO LATE.ITS A CONFIRMED NEWS THAT IT IS NOT GOING TO HAPPEN AND TAKE ALL YOUR MONEY BACK.
Boss please give your residential address we are going to give you all the details personally....arrow group
Deleteso that cyber king is bumped off
DeleteThanks Cyber King for your guidelines
ReplyDeleteHi All,
ReplyDeleteI guess, some Anonymous users are diverting this issue to something else. we are discussing about Arrow issue not Airport or Nava sheva.
The Anonymous which is commenting, he got inside story, That means he knows all this from earlier. So why he invested money ?
This week I will go and meet Arrow and will update you about status. New airport in Mumbai is not having any other option apart from Panvel. Since Navi Mumbai is well planned city as compared to exisiting airport and Kalyan. Which was rumor. Anonymous users Plz provide your name and contact details. So that we can reach you..
hey UTTAMKUMAR,
ReplyDeleteBeing an insider doesnt mean that everything from begining is known,and for the sake of wellness and to save others from the fraudulent biz.i wrote that thing those guys, who think i am correct may do wat i say,but uders u can get trapped into another scam.but the main thing is THIS BULLSHIT IS NOT GOING TO HAPPEN AND THOSE WHO SUPPORT IT GOTO YOUR MOM AND CRY LATER SAYING I WAS CHEATED !
mr Uttamkumar i need your profile. u been talking too loud. will u return my money which is invested in that project, i need to know what u do and wher u are from. please tell ur details.
ReplyDeleteHi,
ReplyDeleteI live in Navi Mumbai but have never heard it. In any case, Pen is quite far from Mumbai/Navi Mumbai, if you are planning to acquire a property with the intention of living close to either of the cities.
While I can't comment on the bonafide of the promoters of this paricular project, I would like to caution you about scores of fly-by-night operators who are out to swindle investors of their hard earned money through dubious projects. There are, however, a few reputed ones too, who deliver what they promise. So please do your home work before investing in any scheme that sounds too good to be true. They may just be!
Hi GoodGirl,
ReplyDeleteHaving moved recently from Navi Mumbai the following is the info. that I can share -
1. Arrow city Manhattan is most likely a dubious bid by the builder / developer to entice HNI to invest. It made a lot of noise couple of years back and now is not to be heard of as much. They were dependent of the trans-harbour link (MTHL) + NM airport to fructify but the latest is that MTHL has been put on the back burner by the govt. until the airport issues gets full environmental clearance. So avoid Arrow city.
2. There are so many high rises being built in Navi Mumbai that it is insane to see so much construction. One good area is the Palm beach marg which has great views of the Elephanta islands & the Thane creek & Arabian sea.
3. Another great development is Kharghar with the area near the central park, Golf course & ISCKON as one of the better ones there.
4. All the above areas have plenty high rises and few independent houses. If you really search then you might find very few in Kharghar or Vashi or even further in Panvel. I doubt if any of those would be brand new ones.
5. If you are looking for brand new independent housing like a second / weekend homes then you might need to go farther than Lonavala as Lonavala has been greatly abused and not worth investing. Some places worth considering are Talegaon, Lavasa, Pavna dam i.e. towards Karjat and then towards Kasara you could look at Khardi, Igatpuri, near Shahapur and then near Nashik. With the expressway nearing completion between Nashik & Mumbai the travel would be a lot comfortable.
Good Luck!
Hi Uttamkumar,
ReplyDeleteWhy do you think this is some kind of advertising. I am just trying to fact find..alright Mintz gave me his opinion, but it does not mean that no one else can give their opinion and morever; one has to fact find and inquire from 10 places before making any decision..so please do not accuse me of something I am not...
Please keep your opinions to yourself.. I don't know about others but I do not need this bad attitude from you..I do not like that you just feel free to insult someone like this.
Treat others the way you would like to be treated...
Please do not send any more replies to my topics...thanks, Ani
Now that the Navi Mumbai Airport Project has received a green signal from the Maharashtra Chief Minister Prithviraj Chavan, Civil Aviation Minister Praful Patel and Environment Minister Jairam Ramesh; the property owners and the real estate owners in Navi Mumbai are much elated with the realty boom in Navi Mumbai. The property prices are expected to touch the skyline even though the work for the proposed Navi Mumbai Airport Project is yet to commence. There are presently many upcoming properties in and around Navi Mumbai. Few of the notable include ongoing constructions at Kharghar, Kalamboli, Nerul, Panvel, Vashi and Airoli. Every single town of Navi Mumbai is prepared to gain with the realty boom in Navi Mumbai and the property prices are expected to soar further with the upcoming Navi Mumbai Airport Project.
ReplyDeleteBut it's not just the upcoming projects that would gain from this realty boom in Navi Mumbai; but even the existing property owners including the 1 BHK flat owners, 2 BHK flat owners or even a small piece of land owner are equally going to gain from this realty boom. A 1- BHK Flat which otherwise would have cost no more than Rs. 18 lacs to Rs. 20 lacs in a city like Airoli or Vashi has seen prices accelerating to Rs. 35 lacs to Rs.40 lacs within these one year, thanks to the then proposed Navi Mumbai Airport Project. Same is the case with a 2 –BHK Flat. A regular 2BHK Flat or an apartment which otherwise would have cost not more than Rs.35 lacs to Rs.40 lacs have accelerated to a whooping Rs. 65 lacs to Rs. 70 lacs. In a similar manner, a normal 100 sq.ft shop which would otherwise cost somewhere around Rs.7 lacs to Rs.10 lacs has seen a considerable raise ranging from Rs. 20 lacs to Rs.25 lacs.
The fact remains unchanged that this had been a known fact by the Navi Mumbaikars as well as the people living in the neighborhoods. The fact that remained unchanged despite of many assumptions, was that the 2nd Airport for Mumbai was going nowhere other than Navi Mumbai. There have been many assumptions and proposed sites where the 2nd airport could have otherwise been shifted, but the airport site at Kharghar was the best option; provided the Green Concerns related to the Environment had been sorted out.
Cities in Navi Mumbai that already have and are in the process of experiencing a considerable realty boom are Kharghar, Vashi, CBD Belapur, Kalamboli, Panvel, Nerul, Airoli, Seawoods, Palm Beach Road, Ghansoli, Rabale etc to name a few. Few upcoming top most residential constructions that are been carried out in Navi Mumbai include the Suntech – Piramal Construction of 30 storey 2BHK Apartments in Airoli, Arihant Aradhana at Kharghar, Prathamesh Construction's upcoming project in Kamothe, Akshar Developer's Valencia at Kalamboli, Akruti Group's Silicon Tower at Vashi etc to name a few. Additionally there are many commercial premises and educational hubs that are present in Navi Mumbai and few more are expected to come up in these couple of years.
This group (Arrow Engg.) is banking and marketing this project on the basis of hypothetical plans which may or may not materialize. I visited the site 3 weeks ago and they've been calling me virtually every day but I don't answer. Here is the reasons why:
ReplyDelete1. Ads have been floating since 3 yrs now but there is no construction done on the site yet
2. They always keep talking about the Sewri-Nhava Seva bridge, new airport & the high speed jetty service which is not yet in place (hypothetical so far)
3. Cost of the property has gone up in the last 3-4 yrs but there is no construction done (except for 1 sample flat on the ground floor)
4. Marking of plots not done on actual site. This makes it difficult for me as an investor to trust these people. In the end, they might allot me just another plot!
I'd say stay away from this project. There are many better investment opportunities at places like Karjat, Shahpur, Alibaug, etc. where you get to see the actual plots.
i will say that why dont we guys get help from that tv reporters, call for consumer complaints CNBC TV HELP LINE
ReplyDeleteEMAIL ADDRESS:
pehredar@network18online.com
ps
lets be united and fix these fuckers.
I too agree with this Idea
DeleteIf so many have gone to the site. Make a recording and send to "CNBC - Citizen Journalist'. Start with this & automatically the professional journalist will cover the story indepth.
DeleteBy the way, I also have invested in Beta Sector C plot & concerned past 4years, however overseas.
PS said,
ReplyDeleteI have also booked Flat and Plot last December 2010 and was concerned regarding the slow progress of project. Hence decided to visit site which I did on 21st October. What I saw is listed below.
1. Site manager took me around the Project site.
2. Entire villagers have been relocated in nearby mound.
3. Three Bungalow are under construction which I went inside and had a look.
4. Met a new Site Engineer who said that he is from Alibagh.
5. Site manager informed that this is the last harvest by local farmers and construction work will start by December.
Picture looked bright from my visit and so let us wait and see.
Even, I have booked a flat and after reading all such negative comments, i am really worried about my invested money. pls keep posted. Thanks, Payal
ReplyDeleteAll above information is misleading. I will request all the investors to please visit Talathi offices of village Kandale, Wadkhal, Dhondpada and Odhangi and ask for village map and see in whose name the 7/12 extracts of the land stand. The lands where Arrow Company is planning to construct their project are mostly salt pan lands. Salt pan lands are owned by government. Salt pans are owned by salt traders of Pen city which includes names like Dharkar and Deo, etc. These salt pan owners have in their employment some managers. These managers have sold possession of salt pan lands to Arrow Engineering Company. These managers and goondas of Arrow Company are threatening salt pan owners and trying to snatch these salt pans from them by using muscle power. Many litigations are to certain in respect of these lands. Most of the plots of salt pan lands are within proposed arrow project. HENCE INVESTORS ARE CAUTIONED HEREWITH. THEY ARE ADVISED TO ASK FOR REVENUE RECORDS OF THESE LANDS.
ReplyDeleteHi Anonymous team, I am not insulting anything.
ReplyDeleteThose who want to know my profile. everybody know my mail id and my name,not like Anonymous. I stay in Navi Mumbai. I am not promoting arrow or any body.
I already invested money in this project.
But here you are misguiding us that airport is not going to happen in panvel like this myths.
For all update, I am directly in touch with Arrow office, Rather than misguiding any thing.
Right now I am out of mumbai, As I will be in Mumbai, I will be meeting Arrow Management personally for this. If required we can file RTI, But without any proof just misguiding us and scaring all investors doesn't make sense.
Those who feel doubtful, they should ask for refund immediately.
For airports facts, I want highlight to all. Navi Mumabi prices and projects are now sky touching.
Indiabull panvel, hiranandani,etc many projects and other all investments happened in panvel. So haev a look on that, Builders are not mad to invest money in panvel and promoting project on basis of airport. Since Builder lobby is having direct access to Govt. decision prior than normal persons. So I dont believe this statement.
I also hope, everything should be in investor favour, Since we invested money with some plans and its our hard earned money.
I am not against anyone and not with anyone in person.
Hope now its clear.
Thanks,
Uttamkumar
Whether flat construction started at Arrow City. Can anybody please update the latest status of site.
ReplyDeleteHi,
ReplyDeleteI have also booked flats in this project, but the way they talk and looking at few comments on the top or any other sites, it looks like same talks of starting project is going on since 2008, now the rains have stopped but still no progress at all.
Whoever like me have invested have to pay the brunt now, but new investors are surely advised think twice before you do so.
Kiran.
I a really confused guys. What should i do. Invest or not??????????
ReplyDeleteis it a fake project?????
had any body done the equiry about same??????
please let me know...
hello every one
ReplyDeleteall have said.......
Ok plz let me know
if all the above said is true then does govt don.t know about this.
Salt lands i think cannot be cultivated with ....
Also such a big project that to fake how can it be
?
? Any one have visited in after 25 dec 11 ? They are telling construction has started......is it so ?
?
Plz let me know i am about to invest in jan 12.
It is wrong to say that salt lands at Pen are owned by government. These lands are in the possession of salt cultivators since unknown time. They were at the mercy of cruel salt officers and opportunistic salt traders. They are used to be deprived of their fundamental constitutional rights due to this unethical association between salt traders and salt officers.
ReplyDeleteThese cultivators are the real owners of salt lands. Documentary evidences in this regard are available in government offices. Above information in respect of salt lands are is wrong.
Having read all the above comments, in details I am really confused. I don't understand is there no one among the Investors, who can use his Good Offices from Maharashtra State Mantrayala & verify regarding the genuineness of the Project. If there is any thing wrong & unlawful, lot of help is available to check the further Fraud by Mr. Arrow City Manhattan Owners.
ReplyDeleteI have also paid some amount for a Flat in Jan. 2011. Till this time I had not been asked to pay the further Installment, & since there no progress on the site it was natural to have doubts. Only this month I have been asked to pay further 10% amount as 2nd installment. But now I am really cautious whether to release the 2nd Installment as demanded by the Co. & also should I withdraw from this Project??
At present, there is some excavation work, which seems to have been taken up recently due to lot of resentment amongst Investors, in addition to a sample Flat & some portion of Boundary Wall. In case, everything would have been on right track, some 10 to 20 buildings would have been completed by this time & possession handed over....
I feel one must think ten times before Investing on this Project.
Dont pay 2nd installment until the builder shows you all approval papers and execute the agreement. I don't think they have got all necessary approvals to start the construction work. Further if you notice their advt in HT, it is said that "SITE DEVELOPMENT STARTED".
Deletehi
ReplyDeleteany body know latest development or news of this arrow project is it going right track or illegal pls somebody know then write and tell me
thanks
Good to see something positive!! Yesterday I visited the location, Construction Work has started- I could see foundation work going on at site, Local staff is confident of finishing the work in next 2 years or so, Though seniors at site were busy playing cricket and very limited workers on job, Have decided to visit the site as frequently as possible for my own peace of mind.
ReplyDeleteMr.Mahesh Agree with you, Currently I received one mailer from Arrow City regarding updates, They said, They will be providing Registrations by this year after March Month. Hope they started some work. Right now I am out of Mumbai.. As I will be back. I will also have personal Visit to office and Pen site.
ReplyDeleteThanks for your Sharing...
Any latest update on this Project please. I am interested in investing in this
ReplyDeleteI BOOKED a 200 sq. mts plot in nov 2011, they r not giving me any registered agreement, only a MOU which shall be notarised and has no value, this all is giving me sleepless nights,my fly says i got in to the wrong project,
ReplyDeleteNo News since last 3 months ! while taking the 2nd Installment for flat booked by me I was promised of Registration within 15 days time, almost 3 months now !! They are yet to contact me for Registration process.
ReplyDeleteLooks like its a bunch of fools discussing about Arrow City.
ReplyDelete1) As mentioned above one of you can file a RTI and know whatever you need, but no one will do it as you are waiting for some one else to do it for you. Its your hard earned money. Go get an RTI done your self. If you do not know how to file it, google it. You have lakhs to invest but not Rs 100 for RTI form.
2) As again mentioned above, looks like its only fools who have invested in this project and have no contacts what so ever to get the details verified.
Arrow promoters might not make good money because they are smart, but they will make money b'cos u r fools.
PS: Did they launch their company on 1 April?
Cheers to you fools...:)
HI FRIENDS, TODAY I WENT TO THE SITE AND WAS HAPPY TO SEE THE CONSTRUCTION WORK IN FULL SWING FOR THE 2 BLDGS ONE IS 2/3 BHK ITS FOUNDATION WORK IS DONE WITH ALL THE PILLARS FOR THE 1STR FLOOR SLAB THE 2ND BLDG FOUNDATION FOR 1/2 BHK ON THE 3RD PLOT THEY ARE DIGGING FOR THE FOUNDATION, ALSO TREES ARE BEING PLANTED AT BETA SECTOR, SO THIS IS A VERY HAPPY NEWS FOR ALL THE MEMBERS ,SO BEST OF LUCK
ReplyDeleteHave u booked a flat? have you verified documents? I wud like to book a one BHK flat but am jittery with all the different comments on this site. Do u know if
Deletethe bank give a loan for purchase of this property?
No good news are coming out here. Future of Arrow city is dark. I have booked one flat in Arrow city but after checking this site i immediately stopped the payment. Now i feel lucky i saved my hard earned money.
ReplyDeleteCan anybody update regarding the flat construction started or not so that we can get a relief.
ReplyDeleteHi All,
ReplyDeleteWe can see the construction site photos on Arrow city website too but, the question is will they really do this time, I mean will they really complete construction of the buildings which they have started in given time and in sooner time will they carry out registration process for Flat as well as for plot which we buyers have purchased from them. I have bought a flat in their project and had made 10% payment for 2BHK, now i will visit the site in coming days and then only can decide whether the further payments should be made or not.
----Girish
hi, i have bought two 300 sq yard plots in the arrow city manhatten in 2008. the big question is legality of the project, and if they have started building the buildings for the flat then it is a good news. they are investing so must be clesr, else a pure land base scheme is dangerous if builder in not investing.
ReplyDeletethe four long term promises were MTHL, mumbai trans harbour link, which is under process and amiguity of mmrda and msrtc has been resolved and given to mmrda, it may see light of the day in coming one- two year and take another 05 years to complete.
second is airport, which has been cleared with some ammendments saving the marshy land and since it is in private hands so will be up and ticking soon is 03- 04 years.
the third was reliance SEZ, the biggest bet because of which arrow city was planned to provide the manpower to SEZ, mukesh ambani took lecture of real estate developers. but sadly it has been scrapped, the reliance is not returning the land which it has acquired, saying it will build small SEZ, god knows what will happen. one other big problem is irrational farmer in the area, who dont give land for any thing, they are fighters and have made a political party to oppose SEZ, and refernadum was done and sez was scrapped. has reliance aquired 75 percent of land rest govt would have acquired and given to them but they could only acquire 30 percent or so.
navi mumbai SEZ is on track and will be functional. can see see NMSEZ website, since govt is too involved in it so no land acquiring problem.
rewas port, the jetty story , it is a private port, which belongs to RIL, it was planned with SEZ, but since SEZ gone the port has been put on back burner by RIL. it is a good port with deep draught and good potential, it will eventually come up once reliance get foot hold on land, else the land price will go up for them.
the big companies are aquiring land banks in the area, as soon as the MTHL is announced this area will be a hit, and MTHL lost track due to fight between anil ambani and mukesh ambani where anil ambani co qouted too low to spoil the mukesh ambani plans to build MTHL, now it is again going to happen soon.
the point i am making is the area has huge potential, and it can get into a fast track development soon with announcement of MTHL.
but the big question is whether the arrow city is legal and has necessary clearances. little delay is understood, 2008 world crashed, so did this project, then it is coming up with slow speed, but it will be all fine if flats are sold off and the project comes up now, but legality is in question.
rajiv baisoya
Sir please give your email id so that we give you legal details
DeleteDear Mr. Vineet,
DeleteI would suggest you publish the leagal documents on your website for clarity. Also if you update your site with construction work and process. These question might not have come. some people will always complain, that is there nature, but you need to create satisfation in customer base. Which I must tell you is missing.
Dear Vineet Malhotra,
DeleteI have booked 2 plots in Beta Sector 3 since 2008/9 & till date just a notarised MOU. By when can I expect theactual plot registration & possesion.
Being overseas, I agree with the above poster to advise your office to update the construction photos on your website, since today this is the best form of monitoring progress.
Rest assured, 2008 was unfortunate to all...however hope City Manhattan sees the Day Light.
Regards
Ferreira
An RTI application would help you know if the Arrow construction site work, lands bought by the builder through proper means is not ? and all dealings is legal or not. This idea was given by High court during a ruling given against the Navi mumbai construction for Green Heritage at kharghar who exceeded FSI given to them.
ReplyDelete-Girish
Sorry mujhe english nahi aati isliye hindi mai likh raa hu...sab flats bookho gaye hai aur yeh wapas se booking kar raha ai jab project complete hoga tab jana apna flat lene ek ke sath ek family free milengi.
ReplyDeleteSorry mujhe english nahi aati isliye hindi mai likh raa hu...sab flats bookho gaye hai aur yeh wapas se booking kar raha ai jab project complete hoga tab jana apna flat lene ek ke sath ek family free milengi.
ReplyDeleteDont pay 2nd installment until the builder shows you all approval papers and execute the agreement. I don't think they have got all necessary approvals to start the construction work. Further if you notice their advt in HT, it is said that "SITE DEVELOPMENT STARTED".
ReplyDeleteIs resale of plots are happening. If yes..can somebody suggest some dealers/agents dealing with this project.
ReplyDeleteEven you asked refund they are cutting your installment 20% and give the remaining money and still work is not so good speed means they are non commitment people. they do not any feeling the people hard money. they earn only investor book and flat and canel the flat. but they earn lots of money. it is shameless, nonsense management and they do not have any commitment all bosses are irresponsible.
ReplyDeleteWe also booked the plots 2.5 yrs ago, paid 1 yr installments and stopped after that. they have even not demanded further money...Whenever we asked for registration, they say it will after 3 months. Now they saying, after mansoon get over. but no concrete commitments from their side.
ReplyDeletePlease visit us for site and your payment updates
Deletedon't say they have not asked for further payment.be grateful otherwise u will be looted more
DeleteDear all ...please visit our site and office at belapur navi mumbai to seek all details. This is a mega project and is being completed in phases....please send your email addresses so that we can send you newsletters regarding our present and future developments at : arrowsales9@gmail.com....we are working 7 DAYS A WEEK so you can clear your doubts any day...please no negative marketing without your name and contacts..we are here to serve you...we have already acquired 1289 acres of land out of 1545acres planned....made 29km of internal roads(wbm) and shall start concreting after monsoons. Three buildings planned as 18floor height have come above ground...all machinery required to complete first phase has been procured...so please be our guest ..visit us...and then please write comments of true nature....Arrow
ReplyDeleteWhen the construction will start for A3 building.
DeleteDear Viineet,
ReplyDeleteWhat happened to A3 building of G+7 storey. When construction will start. Now you are talking about 18 floor building. Please clarify.
Dear Vineet,
ReplyDeleteWhat is the status of A4 building. As per your original layout you had A1 to 4, B1 to 8 and C1 to 4 buildings.
Now you are mentioning 3 buildings of 18 floors. What is the revised layout of these buildings. Are they in addition to all original buildings. Please clarify.
Arrow City Manhattan? No land! No Government Approval! No Proof!
ReplyDeleteThere has been a lot of doubts and questions raised about the status of the Arrow City Manhattan - Panvel/Pen project. There has been no development at site for more than FOUR years. The promoter has not been sharing any information about the project – proof of purchase of land by the Company, approval of building plan by Alibaug Town Planning Department, and all other clearance related issues. There are news about the project being scrapped, although public continue to show interest and make bookings due to huge advertisement and publicity. The company has not been forthcoming about it work schedule at site. The Company sales representative has shown an 7/12 extract of land in the name of the promoter and not in the name of the Company. The Arrow City approval of 2008 is too old a document to understand its current status. It may have been scrapped subsequently. There was another document, known as search report for a piece of land by a private advocate. All these documents mean nothing in real terms. The company has started booing flats for 18 story buildings without even submitting a building proposal for approval to the Government. After waiting for a couple of years, many investors have cancelled their bookings and taken the money back. The company is in profit in every way as it deducts 20% of the money. These are some of the information we received from company sales representative orally and for spot viewing of irrelevant and misleading documents after repeated requests. These do not reflect on the status of the project. There is little hope and serious doubt, that the Company is not serious and sincere about executing the project. Our investment will then be just lost. Please wake up and ask for proof from the company.
Please write a letter to the company and send by registered post with acknowledgement due asking for the following documents:
(1) Copy of 7/12 extract of land on which the your building or plot is to located
(2) Copy of Building proposal approved by the Town Planning Department, Alibaug
(3) Allotment letter for your Flat/Plot
(4) Copy of draft agreement for sale for registration of your booking (this is required to done on booking itself to protect your investment)
(5) Copy of any latest approval or communication from any government department
Some of the investors have come forward to form a discussion group. We welcome you to the eGroup for those who have booked Flats or Plots at Arrow City Manhattan at Pen, MahaMumbai. This is platform to share information and feedback among the Investors. The Company has nothing to do with this eGroup.
We request the investors to join the group.
To Join the discussion group for update and sharing, email to Arrowcity(at)googlegroups(dot)com
If you have any information, write to moderator at ArrowCity.MahaMumbai(at)gmail(dot)com
Please forward this email to everyone you know, who have invested in the project.
Lets join hand to protect our interest collectively! Its our hard earned money!
Dear Arrow,
ReplyDeleteStop all these giving false commitment..you have a team at belapur who dont know anything correct. i hv been visited several times at ur belapur office but all people sitting there are like character of peepli live..who dont wat to say and wat to suggest guest...we have group booked flats in enigma and after chasing also we didnt got any allotment letter yet. we have booked flat in 2010..and 20% has been paid,,its true that u hv management who dont hv any planning like bhagan bharose..we have called several times..at ur belapur office one lady named pallavi everytime she revert that she will call n get back to us since last 3 weeks her revert is still pending..when we asked when we can meet MD..she is scred like i am stranger and character of Crime Petrol-Dastak..
when i asked her when i can meet ur MD who atleast hhave gusts to say fact bt everytime she says.i dont kn when he will come, he is in delhi..i dont hv his no .u dont hv any courtsey to even respond to our call or atleast sent a allotment letter.
i would appreciate if u can tell what is the status of Registration.. While booking u people said that there wont be any cancellation charges till regitration.bt now u are asking for 20% deduction...to be honest we dont trust more..on u..and we all are planning to cancel..pls let us knw the process...
I booked a plot in beeta sector-6 in 2008. I paid almost 90% of the money in emi scheme (by the developer). I am yet to get the plot registered in my name. I am still keeping faith in the project as there is a huge potential of development in the area. It seems, the developer has taken a huge risk in the project anticipating Reliance Mahamumbai- SEZ, Navi Mumbai Airport and MTHL. The developer has not run away from the project as we can see the happening in the area (arrowcity-manhattan). The clarity of acquisition of land by arrow city is not there. That is why financial institutions (HDFC, ICICI SBI, LICHFL etc.) are not approving and giving loan for this project. The risk the developer is taking is naturally passed on us. Let us wait and watch. But there is a huge development potential in this area in the years to come.
ReplyDeleteOf lately they claim that they have got necessary permissions to raise the upto 18 floors ... but on questioning on the new floor plans they say that the new floor plans will be available in 2 months. Is it true? Also when I asked about an area for fire fire exits in high rise buildings ... their executive said that he was not aware about any such thing :(
ReplyDeleteHi I have bought a flat at Arrow Manhattan, last week I visited belapur office where i met Mr Satish Sharma and i asked about the progress,he told there is a dispute going on with the farmers for the aquisition of land but will be cleared in next 3 months. I told him to take me to the site for viewing the progress,he refused me to take to the site and insisted me to buy a plot in nasik which would gurantee the security. I found him little suspicious and asked him i want to meet the managing director,h said Md Mr vineet Malhotra stays in Bangkok for their new manhattan project in Bangkok. He guided me to the Director Mr Shrikant, who has some communication problems,could not help me.Pls do let me know whether this project is real or fake.
ReplyDeleteMr Ahmed
its fake dear just tel him give ur all money back with int....or move to poilce u wil get ur all money
DeletePlease share current status of the Beta Sector Plots, if you have visited the site recently & has any investor in this project done his legal final registration with Arrow Eng Ltd.
ReplyDeleteThis would be beneficial to all mankind. Thanks you for your contribution.
ReplyDeleteLand Grab by Arrow City??
ReplyDeletehttp://timesofindia.indiatimes.com/city/mumbai/Salt-department-red-flags-bid-to-grab-950-acres/articleshow/19979507.cms?
Respected Sir
ReplyDeleteThanks a lot for your support.We have been working very hard on development front. The access road work (apprx. 29 kms) has been done in Beta Sector (plot area). We are planning to start registerations once permissons are granted by the government this might take couple of months more as along with already taken permissons and already submitted we have to apply to cidco airport township authority , which we would be able to apply only once development plan of cidco is approved by the government of maharashtra .we will inform you in advance for the same as we are going to send newsletter to all of our clients by end of next month regarding development plan of coming six months.
Sample bungalows are ready at site. Construction of seven buildings is also going on at site .We have also set up a factory for hollowcore Slab machines , sewerage pipe for plot machines etc and all machines have come to site and we plan to commence production by next month at site..Once again thanks a lot for being with us.Please revert in case of any query and visit me at site on any working day.
Regards
Gaurav Khanna
Director
Arrow Engineering ltd.
www.arrowgroup.us
All approvals received by us can be downloaded at website
this is fake project do not invest.
ReplyDeleteproject engineer sandep jain is bogus engineer & many fraud are involvedin it .
investers raise FIR to nearest police stations .
Dear all investers,
ReplyDeleteThis project engineer's are having fake degrees .,Fraud cases .
All investers requested to log police FIR to nearest stations .
all affidivates done of 8000 rs are fake.
No stamp duty registration done .
total 2500 investers are fulled year with 25 corer daily interst on there investments .
government not gave permission for this til they full all that 21 floors permission recieved.
sandeep jain has police fraud record who is project engg
Any updates about 7 storied buildings construction.
ReplyDeleteWhat will happen in case the builder transferring right to the flat owners as land owner
ReplyDeleteHi Friends, no update since "May 12, 2013 at 2:18 PM". Can someone please let me know about the progress and latest update on Arrow City project ?
ReplyDeleteThanks, Rupesh
Anticipatory bail is rejected by Supreme Court for Arrow City Directors Vineet Ramesh Malhotra and Gourav Khanna on 11th Sept 2017 :
ReplyDeleteAnticipatory bail is rejected by Bombay High Court for Arrow City Directors Vineet Ramesh Malhotra and Gourav Khanna on 22nd August 2017 :
ANTICIPATORY BAIL APPLICATION NO. 1452 OF 2016
Anticipatory Bail Applications are filed for relief of anticipatory bail in Crime No.15 of 2016 which is registered in Wadkhal Police Station, District Raigad, for the offences punishable under Sections 420, 409, 34 of the Indian Penal Code and Sections 3, 4, 8, 11, 13 and 14 of Maharashtra Ownership Flat Act, 1963.
Important Details of the order are as Below : ( Full order is available on Bombay High court website )
• In the year 2007 when the amount was accepted by the Applicants from thousands of persons, no project was in its place. Even the proposal of the project specifying the properties was not there and due to that it can be interfered that there was intention to deceive only to collect the money.
• There is no record produced by the Applicants even when interim protection was given to them to show that account of the company was opened and the money collected was deposited in the said account. On this the learned Counsel for the Applicants submitted that properties were to be purchased and so the amount was not kept in such account.
• In brochure which was prepared subsequently the total area of the land which was to be used was shown as 1545 acres but not even 10% of this amount was owned by the company. Even in the proposal considered by the concerned department of this company in the year 2009 it was shown that the land to the extent of only 5.6% was purchased. The land to the extent of 29% was to be obtained from the Government under lease which was not possible and some land was to be procured from the Government which was 22.2%. Thus when no land was fixed for the development and creation of the township, money was collected.
• Even when it was clear that development of the property was not possible after the year 2013 as the CIDCO was the authority, attempt was made again to deceive the persons who had paid the amount by asking them to execute agreements of joint development
• It was submitted that indirectly Vineet Malhotra has deceived in one more way. One property was purchased in the name of Vinit Malhotra for the consideration of Rs.38,00,000/in the year 2010 and the some property is shown to be sold to the company for the consideration of Rs.1.60 crore in the year 2013. This circumstance again shows that whatever money was collected from poor persons was obtained directly or indirectly by persons like Vinit Malhotra.
• Custodial interrogation is a must and only after custodial interrogation the amount which is collected by deceiving the persons can be recovered and that can be done even by attaching the properties of the company and the Applicants. It appears that the provisions of Maharashtra Ownership Flat Act, 1963 are also used in the present matter.
• Before publishing the project and accepting the money, it was the responsibility of the persons like Applicants to anticipate all these things and then prepare project on the basis of the land which was actually available. It can be said that there is not a single document with the Applicants to show that such procedure was followed. This circumstance shows that right from beginning they had the intention to deceive. They have actually used the public money by not showing that money in the account of company. This is nothing but misappropriation of the money entrusted to them.
For the reasons already given this Court holds that discretionary relief cannot be given to the Applicants in Anticipatory Bail Application No.1452 of 2016 and their Application stands rejected. Adinterim relief, if any, granted in their favour stands vacated.
Can i known who all have invested now were has project gone iys now 2019 y didnt they start project yet plz tell me any one